Timeline
Start on site: February 2010
Site clearance: March 2010 to April 2010
Commence installation of foundations for structures: July 2010
Refurbishment of Japanese and Chinese structures: June 2010 to November 2010
Installation of new bridge structures: September 2010
Commence planting to garden areas: September 2010
Re-fill watercourses: November to January 2010
Site completion: March 2011